20 hoteliers opt out of 2010 Games project
20 hoteliers opt out of 2010 Games project
This has resulted in shortage of about 5,000 proposed rooms.

New Delhi: About 20 hoteliers have opted out of the Commonwealth Games hotel project putting severe strain on the Government for providing accommodation to guests of the upcoming mega sporting event.

Aiming at providing 40,000 rooms during the 2010 Games, the Delhi Development Authority (DDA) had auctioned 33 hotel plots in the Capital.

Of the total hoteliers who bagged the project, 20 have not even completed 30 per cent of ground work and have considered opting out, a senior Tourism Ministry official told PTI.

“For example, Amar Hospitality which was to construct a 512 room hotel in Shahadara, is moving at a snail’s pace and there are not much activity on the ground. For us, they have opted out of the Games project,” said the official.

Similarly, Asrani Inns is yet to make any headway in constructing two hotels with 375 rooms at Wazirpur. The 219-room hotel at Rohini by Breaze Constructions is also delayed and the Government is firmly ruling out its inclusion.

Work progress of Anush, which was given land in Shahadara for construction of a 136-room hotel, is tardy. Even 30 per cent of the work is not completed as per the status report.

IFCI Ltd was given land in Mayur Vihar for building a hotel with 91 rooms, Sewa Hotel was to come up with 72 rooms in Pitampura and Brilliant committed to construct 138 rooms at Shalimar Bagh. The Ministry has put these rooms in doubtful category after their work almost stopped.

The opting out of majority of the hoteliers has resulted in shortage of about 5,000 proposed rooms.

While some hoteliers have cited fund crunch due to the global meltdown for the delay, others have given procedural wrangles and floor area ratio among the reasons for developing cold feet in completing the hotel projects before the 2010 Games, the official said.

Construction major DLF, which was to build 800 rooms at Dwarka City, according to the status report, is way behind schedule.

Similar is the case with the Emaar MGF which was supposed to come up with 122 rooms at Jasola but their rooms have now been put under doubtful category.

DJ Infrastructure has got land at central Delhi in Motia Khan to construct a 190-room hotel. But only 20 per cent work has been completed and the project is now being ruled out from the Commonwealth Games project.

“We are going ahead with the alternative plan without depending on these hotels,” said the official.

As per the alternative plan, there will be 10,268 rooms from new hotels, about 11,000 rooms from guest houses, 3,000 rooms from the Bed and Breakfast scheme and 5,500 rooms from DDA housing units besides the 10,150 rooms already available.